CompTIA Project+ (PK0-004) — Question 530
A project, which is nearing completion, is ahead of schedule and under budget. However, to improve quality to acceptable levels, the project will require additional time.
Which of the following BEST describes this scenario?
Answer options
- A. Score creep
- B. Interactions between constraints
- C. Constraint reprioritization
- D. Change request
Correct answer: B
Explanation
The scenario illustrates how different project constraints, such as scope, time, and cost, interact with each other, making 'Interactions between constraints' the best description. 'Score creep' refers to uncontrolled changes in project scope, which is not the issue here. 'Constraint reprioritization' suggests changing the priority of constraints, while 'Change request' implies a formal request to modify project elements, neither of which accurately capture the essence of the situation.