CompTIA Project+ (PK0-004) — Question 53

A project manager would like to bring vendors into a new project. Which of the following documents should the potential vendors submit so the project manager can find the best vendors for the project?

Answer options

Correct answer: B

Explanation

The correct answer is B, the Statement of Work (SOW), as it outlines the specific tasks, deliverables, and timelines that vendors are expected to adhere to. Options A (SLA) pertains to service level agreements which define service expectations, C (Change request) is for requesting modifications to existing agreements, and D (RFP) is a request for proposal that solicits bids but does not detail specific work requirements.