CompTIA Project+ (PK0-004) — Question 52

Which of the following activities are associated with the closing phase of a project? (Choose two.)

Answer options

Correct answer: B, D

Explanation

The correct answers, B and D, pertain to the finalization of a project where archiving documents and capturing lessons learned are essential for future reference and improvement. In contrast, A (Risk mitigation), C (Tracking of expenditures), and E (Quality assurance) are activities more relevant to the execution and monitoring phases of a project.