CompTIA Project+ (PK0-004) — Question 52
Which of the following activities are associated with the closing phase of a project? (Choose two.)
Answer options
- A. Risk mitigation
- B. Archiving of project documents
- C. Tracking of expenditures
- D. Lessons learned
- E. Quality assurance
Correct answer: B, D
Explanation
The correct answers, B and D, pertain to the finalization of a project where archiving documents and capturing lessons learned are essential for future reference and improvement. In contrast, A (Risk mitigation), C (Tracking of expenditures), and E (Quality assurance) are activities more relevant to the execution and monitoring phases of a project.