CompTIA Project+ (PK0-004) — Question 513
At each project team meeting, the project team raises the same risk repeatedly. A mitigation plan has been developed since the risk was initially identified.
Which of the following risk activities is MOST likely missing since the identification?
Answer options
- A. Quantification
- B. Response
- C. Prioritization
- D. Communication
- E. Review
Correct answer: E
Explanation
The correct answer is E, Review, because it indicates that the team may not be revisiting the risk to assess its current status and effectiveness of the mitigation plan. Options A (Quantification), B (Response), C (Prioritization), and D (Communication) are typically part of the risk management process but do not specifically address the ongoing evaluation of the risk after its initial identification.