CompTIA Project+ (PK0-004) — Question 505
A new corporate policy was approved that will positively affect the project.
Which of the following should the project manager do FIRST?
Answer options
- A. Schedule the change
- B. Review the communication plan
- C. Update the issue log
- D. Update the risk register
Correct answer: B
Explanation
The correct answer is B because reviewing the communication plan is essential to ensure that all stakeholders are informed about the new policy and its implications for the project. Options A, C, and D may be necessary steps later, but they are not the immediate priority without first communicating the changes to the team and stakeholders.