CompTIA Project+ (PK0-004) — Question 505

A new corporate policy was approved that will positively affect the project.
Which of the following should the project manager do FIRST?

Answer options

Correct answer: B

Explanation

The correct answer is B because reviewing the communication plan is essential to ensure that all stakeholders are informed about the new policy and its implications for the project. Options A, C, and D may be necessary steps later, but they are not the immediate priority without first communicating the changes to the team and stakeholders.