CompTIA Project+ (PK0-004) — Question 504

Which of the following documents should the project manager complete if requirements have been defined, but neither a vendor nor a platform has been identified?

Answer options

Correct answer: A

Explanation

The correct answer is RFP (Request for Proposal), which is used to solicit proposals from vendors when the requirements are clear but the provider is not chosen. RFQ (Request for Quotation) is typically used when prices are needed, RFI (Request for Information) is for gathering information before narrowing down options, and SOW (Statement of Work) outlines specific work but does not request bids.