CompTIA Project+ (PK0-004) — Question 504
Which of the following documents should the project manager complete if requirements have been defined, but neither a vendor nor a platform has been identified?
Answer options
- A. RFP
- B. RFQ
- C. RFI
- D. SOW
Correct answer: A
Explanation
The correct answer is RFP (Request for Proposal), which is used to solicit proposals from vendors when the requirements are clear but the provider is not chosen. RFQ (Request for Quotation) is typically used when prices are needed, RFI (Request for Information) is for gathering information before narrowing down options, and SOW (Statement of Work) outlines specific work but does not request bids.