CompTIA Project+ (PK0-004) — Question 477
Which of the following captures unforeseen activities throughout the project that need attention and resolution?
Answer options
- A. Gantt chart
- B. Action items
- C. Project schedule
- D. Meeting minutes
Correct answer: B
Explanation
Action items are specific tasks or activities that arise during a project and require attention to address issues. Gantt charts, project schedules, and meeting minutes do not inherently capture unforeseen activities; they serve different purposes in project management.