CompTIA Project+ (PK0-004) — Question 476

A project manager needs status on the project timeline.
Which of the following team members should provide an update?

Answer options

Correct answer: C

Explanation

The Scheduler is responsible for maintaining the project timeline and can provide the most accurate updates regarding its status. The Product owner and Business analyst may not have detailed insights into the scheduling, while the Sponsor typically focuses on high-level oversight rather than day-to-day project details.