CompTIA Project+ (PK0-004) — Question 472

A project manager has contracted a third-party vendor to achieve milestones. Which of the following risk strategies is the project manager applying?

Answer options

Correct answer: A

Explanation

The correct answer is A, Transfer, as the project manager is shifting the responsibility of achieving milestones to a third-party vendor. The other options are incorrect because Accept means acknowledging the risk, Avoid involves eliminating the risk, and Mitigate refers to reducing the impact or likelihood of the risk, none of which apply in this scenario.