CompTIA Project+ (PK0-004) — Question 471
A project in the execution phase is over budget, and tasks on the critical path are on schedule.
Which of the following should the project manager do NEXT?
Answer options
- A. Update the project management plan.
- B. Issue a change request.
- C. Revise the project charter.
- D. Evaluate the impact to the baseline.
Correct answer: D
Explanation
The correct action is to evaluate the impact to the baseline, as it helps the project manager understand how the over-budget situation affects the project's overall plan. Updating the project management plan, issuing a change request, and revising the project charter are important but should follow after assessing the baseline impact.