A project in the execution phase is over budget, and tasks on the critical path are on schedule.
Which of the following should the project manager do NEXT?

Answer options

Correct answer: D

Explanation

The correct action is to evaluate the impact to the baseline, as it helps the project manager understand how the over-budget situation affects the project's overall plan. Updating the project management plan, issuing a change request, and revising the project charter are important but should follow after assessing the baseline impact.