CompTIA Project+ (PK0-004) — Question 463
The president of a company is pushing to get a product on the market before a competitor releases a similar one. The project manager does not believe the current resources for the project are adequate to meet the deadline. Which of the following is the BEST resource management approach for this scenario?
Answer options
- A. Trust-building
- B. Subject matter experts
- C. Fast track
- D. Forcing
Correct answer: C
Explanation
The best approach in this scenario is to utilize fast tracking, which allows overlapping project phases to expedite the timeline. Trust-building and subject matter experts may enhance the project but do not directly address the immediate need for speed, while forcing may lead to conflicts and reduce team morale.