A key stakeholder reviews the project charter and expresses concern that the milestones are not documented. Which of the following should the project manager do?

Answer options

Correct answer: B

Explanation

The correct answer is B because adding baselines to the charter ensures that milestones are formally documented, which addresses the stakeholder's concern. Option A is incorrect as simply reviewing the project management plan does not resolve the issue of missing milestones. Option C does not provide a solution but rather documents a concern without action. Option D provides current project information but doesn't address the documentation issue at hand.