CompTIA Project+ (PK0-004) — Question 461
A key stakeholder reviews the project charter and expresses concern that the milestones are not documented. Which of the following should the project manager do?
Answer options
- A. Direct the key stakeholder to review the project management plan
- B. Add the baselines to the charter after a change request has been approved
- C. Document the key stakeholder’s concerns in the issue log
- D. Provide the key stakeholder with a status report to show where the project currently stands
Correct answer: B
Explanation
The correct answer is B because adding baselines to the charter ensures that milestones are formally documented, which addresses the stakeholder's concern. Option A is incorrect as simply reviewing the project management plan does not resolve the issue of missing milestones. Option C does not provide a solution but rather documents a concern without action. Option D provides current project information but doesn't address the documentation issue at hand.