CompTIA Project+ (PK0-004) — Question 449

Which of the following is the MOST likely number of phases in waterfall project management?

Answer options

Correct answer: B

Explanation

The correct answer is B, as the waterfall model typically consists of five distinct phases: requirement gathering, design, implementation, verification, and maintenance. Options A, C, and D do not accurately reflect the standard phases in this project management methodology.