CompTIA Project+ (PK0-004) — Question 438
A project is in the initiation phase. Which of the following tasks will take place during this phase?
Answer options
- A. Develop a WBS.
- B. Define the project requirements.
- C. Create a project charter.
- D. Acquire the project resources.
Correct answer: C
Explanation
The correct answer is C, as creating a project charter is a fundamental task in the initiation phase, establishing the project's purpose and objectives. Options A and D are tasks that occur in later phases, while option B, although important, is generally more detailed and defined in subsequent planning phases.