CompTIA Project+ (PK0-004) — Question 417
A project manager needs to track the actual and estimated start and finish dates of all WBS work packages.
Which of the following is a necessary step to record the actual durations?
Answer options
- A. Establish each WBS work package resource.
- B. Establish and set the baseline.
- C. Establish and set the quality gates.
- D. Establish the tollgates.
Correct answer: B
Explanation
The correct answer is B because establishing and setting the baseline allows the project manager to compare actual performance against the planned dates. Options A, C, and D do not directly involve tracking actual durations; they focus on resource allocation, quality assurance, and project milestones respectively.