CompTIA Project+ (PK0-004) — Question 416

A project team member highlights to the project manager that expensive licensing for critical software in use across the project may expire before the completion project.
Which of the following would the project manager MOST likely do?

Answer options

Correct answer: A

Explanation

The correct answer is A because placing a risk on the risk register and reviewing it with stakeholders is a proactive approach to managing potential issues. Options B, C, and D do not address the risk of license expiration adequately, as they involve either immediate purchases, scope changes, or removing essential software rather than managing the risk itself.