CompTIA Project+ (PK0-004) — Question 414
A new project charter is being drafted.
Which of the following would be the BEST source for the high-level project requirements?
Answer options
- A. Sponsor
- B. Project manager
- C. Project management office
- D. Project team
Correct answer: A
Explanation
The sponsor is typically the individual or group that provides the funding and support for the project, making them the best source for high-level requirements. While the project manager and project management office may contribute to the project, they usually rely on the sponsor's vision and objectives. The project team is focused on execution and may not have insight into the overarching requirements.