CompTIA Project+ (PK0-004) — Question 403
Which of the following describes a burn rate?
Answer options
- A. The rate at which project documents are disposed.
- B. The rate at which project personnel leave the project.
- C. The rate at which the project budget is used.
- D. The rate at which the timeline increases.
Correct answer: C
Explanation
The correct answer is C because burn rate specifically refers to the amount of budget that is utilized over a certain period. The other options describe different aspects of project management but do not accurately define burn rate.