CompTIA Project+ (PK0-004) — Question 402
A project manager is justifying a required change with the associated impact on the project.
Which of the following is the NEXT step?
Answer options
- A. Implementation
- B. Approval
- C. Validation
- D. Auditing
Correct answer: B
Explanation
The next step after justifying a change is to seek Approval from stakeholders, as it is essential to obtain consent before proceeding. Implementation cannot occur without approval, while validation and auditing are steps that typically follow after changes are approved.