CompTIA Project+ (PK0-004) — Question 379
A project manager is reviewing a project's status and finds that while it is 25% under budget, there are significant quality defects, and the project is behind by six weeks.
Which of the following should the project manager increase to BEST resolve this issue?
Answer options
- A. Resources
- B. Quality
- C. Schedule
- D. Scope
Correct answer: A
Explanation
Increasing resources is the best approach to address the quality defects and delays, as more personnel or tools can help expedite the work and improve quality. Simply increasing quality may not resolve the underlying issues causing defects, while adjusting the schedule or scope could exacerbate the problem rather than solve it.