CompTIA Project+ (PK0-004) — Question 378
A new project manager receives important deliverables from a team member at odd hours. The quality of the deliverables is acceptable, but the project manager is concerned that the team member is not prioritizing work correctly. This is MOST likely due to:
Answer options
- A. time zones
- B. language barriers
- C. technological factors
- D. intraorganizational differences
Correct answer: A
Explanation
The correct answer is A, as time zone differences can lead to asynchronous work hours, causing team members to submit deliverables at unconventional times. The other options, while they may present challenges, do not directly relate to the timing of deliverables as effectively as time zones do.