CompTIA Project+ (PK0-004) — Question 375

During a project, the project manager realizes some staff positions may be eliminated. Which of the following is the best NEXT step for the project manager to take?

Answer options

Correct answer: B

Explanation

The best next step is to identify replacement resources to ensure the project can continue effectively despite potential staff reductions. Communicating with the project sponsor, reviewing the schedule, or adding the risk to the risk register does not address the immediate need for resource availability.