CompTIA Project+ (PK0-004) — Question 370

A project team learns that potential remodeling on the production floor might occur during the execution phase of their project. The project team starts debating the different options available to keep delivering without adjusting the schedule. Which of the following risk activities is being performed?

Answer options

Correct answer: A

Explanation

The correct answer is A, Mitigation, as the team is actively looking for ways to address and reduce the impact of the potential remodeling on their timeline without changing the schedule. Options B, C, and D do not accurately describe this proactive approach; Quantification involves assessing risk levels, Planning focuses on creating strategies, and Identification pertains to recognizing risks rather than addressing them.