During a sprint, the product owner asks the scrum master to work on a quality issue as soon as possible. Which of the following is the scrum master's MOST likely action?

Answer options

Correct answer: C

Explanation

The correct answer is C because the scrum master needs to escalate the issue to upper management to address the quality concern appropriately. Options A and B do not directly address the urgency of the request, and option D merely informs the product owner of delays without taking action on the issue.