During a sprint, the product owner asks the scrum master to work on a quality issue as soon as possible. Which of the following is the scrum master's MOST likely action?
Answer options
- A. Advise the product owner to submit a change request to the CCB.
- B. Ask the product owner if the issue can be deferred to the next sprint.
- C. Escalate the request by the product owner to upper management.
- D. Inform the product owner of potential delays to the work in the sprint.
Correct answer: C
Explanation
The correct answer is C because the scrum master needs to escalate the issue to upper management to address the quality concern appropriately. Options A and B do not directly address the urgency of the request, and option D merely informs the product owner of delays without taking action on the issue.