CompTIA Project+ (PK0-004) — Question 366

Two weeks before reaching a major milestone, an unidentified risk is realized. The risk will have a profound effect on the financial health of the project, nearly doubling the actual costs to complete the work. Which of the following is the BEST action for the project manager to consider?

Answer options

Correct answer: C

Explanation

The correct answer is C because triggering the incident response plan allows the project manager to collaboratively gather input from participants on how to address the newly realized risk effectively. Option A delays immediate action, B continues the project without addressing the risk, and D is too drastic as it halts the project without first seeking solutions from the team.