CompTIA Project+ (PK0-004) — Question 365
Ann, a project sponsor, is concerned by how long issues remain open before being brought to her attention. Which of the following would be BEST way for the project manager to increase Ann's visibility on issues?
Answer options
- A. Tailor the status reports to bring only certain information forward.
- B. Provide more detail in the regular status reports.
- C. Schedule daily, face-to-face meetings with Ann.
- D. Increase the frequency of the status reports.
Correct answer: A
Explanation
The correct answer is A because tailoring the status reports to highlight key issues allows Ann to quickly identify and focus on the most critical information, thus increasing her visibility. Options B and D may overwhelm her with too much information, while C could be impractical and time-consuming.