CompTIA Project+ (PK0-004) — Question 362
Because a feature was not meeting documented requirements, a project milestone was not achieved as scheduled. Which of the following activities should the project manager perform NEXT?
Answer options
- A. Calculate the schedule variance and update the project status.
- B. Update the project scope and obtain sponsor approval.
- C. Review quality control processes and make the necessary improvements.
- D. Schedule a meeting with stakeholders and update the project objectives.
Correct answer: D
Explanation
The correct answer is D because scheduling a meeting with stakeholders allows for aligning the project objectives with the current situation and ensures everyone is informed and involved in the decision-making process. Options A, B, and C focus on internal adjustments rather than engaging stakeholders to reassess and realign project goals, which is crucial after missing a milestone.