CompTIA Project+ (PK0-004) — Question 36

A project manager has received a change order that will reduce a project's timeline and budget. However, the change order also indicates the goals and deliverables of the project must remain unchanged. Which of the following is the MOST logical impact to the project?

Answer options

Correct answer: B

Explanation

Option B is correct because a reduced budget typically means fewer resources are available, which may necessitate a strong matrix organizational structure to manage the project effectively. The other options do not logically follow from the conditions presented; for instance, a reduced timeline generally increases risk rather than decreases it (as stated in option C), and rejecting the change order (option D) is not a guaranteed response to budget changes.