CompTIA Project+ (PK0-004) — Question 321
A company is conducting a project that is expected to have positive effects on a local town. The townspeople are excited about the project and want to help make it a success, but they are nervous because updates have not been released for a while. Which of the following explains how the project manager can ensure the project is a success?
Answer options
- A. Issue a regularly scheduled social media message highlighting the benefits to the town.
- B. Add key townspeople to the project team to ensure they are involved.
- C. Provide the town's government officials with regular verbal updates.
- D. Add townspeople gate reviews to the project schedule.
Correct answer: C
Explanation
The correct answer is C because providing regular verbal updates to government officials keeps them informed and engaged, which can foster support for the project. While option A may raise awareness, it doesn't directly address the need for consistent communication with key stakeholders. Option B could increase local involvement but might not be feasible or effective without formal updates. Option D, while valuable, doesn't ensure that critical information reaches decision-makers effectively.