CompTIA Project+ (PK0-004) — Question 320
An anticipated risk event occurred, and the project risk register was updated. Which of the following is the NEXT document that needs to be updated?
Answer options
- A. Issue log
- B. Mitigation plan
- C. Milestone list
- D. Project plan
Correct answer: D
Explanation
The Project plan needs to be updated next because it encompasses the overall strategy and details of the project, which would include any changes stemming from the risk event. The Issue log, Mitigation plan, and Milestone list may also require updates, but the primary document that reflects the project's current state and adjustments is the Project plan.