CompTIA Project+ (PK0-004) — Question 32
A project is about to begin the execution phase. The SOW and project plan have been approved, and the project team has been formed. Which of the following types of meetings should happen NEXT?
Answer options
- A. Update
- B. Scheduling
- C. Kickoff
- D. Review
Correct answer: C
Explanation
The correct answer is C, as a Kickoff meeting is essential at the start of the execution phase to align the team and clarify project goals. Options A, B, and D are not suitable at this stage, as they pertain to updates, scheduling, or reviews that typically occur after the project has commenced.