CompTIA Project+ (PK0-004) — Question 31

A project has fallen behind schedule for no obvious reason, so the PM has gathered the team to brainstorm. Which of the following should the PM do NEXT?

Answer options

Correct answer: B

Explanation

The correct answer is B because it focuses on identifying specific tasks that are falling behind and understanding where slack exists, which is essential for realigning the project. The other options, while potentially useful in broader contexts, do not directly address the immediate need to understand the current project status and its timeline issues.