CompTIA Project+ (PK0-004) — Question 296
To control costs, project funding is being released under a waved approach. After passing each milestone, the project receives the next round of funding. Which of the following is hindered by this funding approach?
Answer options
- A. Resource sharing
- B. Crash schedule
- C. Burn rate
- D. Team outsourcing
Correct answer: A
Explanation
The waved approach to funding can restrict resource sharing because resources may not be available until the next funding round is secured. This delay can prevent teams from utilizing shared resources efficiently. The other options, such as crash schedule, burn rate, and team outsourcing, are less directly affected by the timing of funding releases.