CompTIA Project+ (PK0-004) — Question 294
A company accepts a proposal from a third-party vendor to provide staffing. Which of the following documents should the project manager create NEXT?
Answer options
- A. SLA
- B. SOW
- C. LOI
- D. RFQ
Correct answer: C
Explanation
The correct answer is C, LOI (Letter of Intent), which outlines the agreement between the company and the vendor before formal contracts are drawn up. The other options, while related to project management, do not specifically serve as a preliminary agreement to indicate intent to move forward with the vendor's proposal.