CompTIA Project+ (PK0-004) — Question 282

A project manager is overseeing an outsourced team of contractors and subcontractors. One month into the project, the project manager realizes tasks are not being completed on time. Subcontractors are not available at the right time.
Which of the following is the NEXT step for the project manager to take to get the project back on track?

Answer options

Correct answer: D

Explanation

The correct answer is D because having a meeting with management can lead to strategic guidance and approval for necessary changes to improve project execution. Options A, B, and C do not directly address the immediate need for managerial approval or strategic realignment to get the project back on schedule.