CompTIA Project+ (PK0-004) — Question 274
Which of the following is the BEST indicator of project failure?
Answer options
- A. Product deficiencies revealed during the monitor and control phase
- B. Project team members disagreeing on milestones
- C. Project deliverables completed behind schedule
- D. Several changes being made to the project
Correct answer: A
Explanation
The best indicator of project failure is the presence of product deficiencies during the monitor and control phase, as this suggests fundamental issues with the project's quality and direction. While disagreements on milestones, delays in deliverables, and frequent changes can indicate problems, they do not directly reflect the inherent quality issues that can lead to project failure like product deficiencies do.