Which of the following is the BEST indicator of project failure?

Answer options

Correct answer: A

Explanation

The best indicator of project failure is the presence of product deficiencies during the monitor and control phase, as this suggests fundamental issues with the project's quality and direction. While disagreements on milestones, delays in deliverables, and frequent changes can indicate problems, they do not directly reflect the inherent quality issues that can lead to project failure like product deficiencies do.