CompTIA Project+ (PK0-004) — Question 273

A project is nearing the expected completion date, but it is behind schedule. The project manager has decided to fast-track the resources.
Which of the following impacts will MOST likely occur? (Choose two.)

Answer options

Correct answer: A, E

Explanation

When resources are fast-tracked, it often leads to increased costs due to the need for additional resources or overtime payments, which is why options A and E are correct. The other options, such as B, C, D, and F, do not accurately reflect the likely impacts of fast-tracking, as scope and quality may suffer while risks generally increase.