CompTIA Project+ (PK0-004) — Question 262
A project sponsor wants to know when the plan changed to ship the deliverables to a new location. To determine the answer, the project manager should FIRST review the:
Answer options
- A. project management plan
- B. scope statements and issue log
- C. project dashboard and status report
- D. action items and meeting minutes
Correct answer: B
Explanation
The correct answer is B because the scope statements and issue log will provide detailed insights into any changes made during the project, including modifications in shipping plans. The project management plan (A) is broader and may not pinpoint the specific change, while the project dashboard and status report (C) focus on overall project status rather than detailed changes. Action items and meeting minutes (D) might not capture all relevant changes comprehensively.