CompTIA Project+ (PK0-004) — Question 261
A project has been experiencing some difficulties due to third-party vendors. The project manager should request.
Answer options
- A. Additional resources
- B. A gate review
- C. A risk register update
- D. A performance audit
Correct answer: C
Explanation
Requesting a risk register update is crucial as it helps identify and assess the risks associated with third-party vendors. The other options, while potentially useful, do not directly address the immediate need to manage the risks impacting the project.