A project has been experiencing some difficulties due to third-party vendors. The project manager should request.

Answer options

Correct answer: C

Explanation

Requesting a risk register update is crucial as it helps identify and assess the risks associated with third-party vendors. The other options, while potentially useful, do not directly address the immediate need to manage the risks impacting the project.