CompTIA Project+ (PK0-004) — Question 252
Which of the following can a project manager use to keep track of finances and ensure costs are accurately applied to a project?
Answer options
- A. PO numbers
- B. Cost baseline
- C. Bill of materials
- D. WBS codes
Correct answer: B
Explanation
The correct answer is B, as a cost baseline is a crucial component in project management that provides an approved version of the budget, allowing tracking and comparison of actual costs. Options A, C, and D do not serve the primary purpose of managing and tracking project finances effectively.