CompTIA Project+ (PK0-004) — Question 250
A project team is defining detailed risks. Which of the following project phases is taking place?
Answer options
- A. Initiation
- B. Monitor and control
- C. Execution
- D. Planning
Correct answer: D
Explanation
The correct answer is D, Planning, as this phase involves identifying and analyzing risks in detail. Initiation focuses on the project's overall feasibility, while Monitor and Control deals with tracking project progress, and Execution is about implementing the project plan.