CompTIA Project+ (PK0-004) — Question 245

A team member was assigned a new task during a meeting. The team member did not complete the task by the end of the phase, and the PM is looking for evidence to escalate the issue. Which of the following documents could help in this situation?

Answer options

Correct answer: A

Explanation

The Issue log is designed to track problems and their resolutions, making it the most relevant document for escalating issues related to uncompleted tasks. While Action items may list tasks, they do not document issues arising from them, and Dashboard information and Communication plans do not provide specifics on task completion status.