CompTIA Project+ (PK0-004) — Question 241
During a routine risk review, the project champion analyzes the status of multiple projects. A potential risk is discovered that will delay project A due to the interdependencies with project B. The project champion schedules a meeting with the project managers. Which of the following risk activities is MOST likely happening?
Answer options
- A. Identification
- B. Registration
- C. Quantification
- D. Qualification
Correct answer: D
Explanation
The correct answer is D, Qualification, as it involves assessing the potential impact of identified risks on project objectives. Identification focuses on recognizing risks, Registration is about documenting them, and Quantification assesses their likelihood and impact, which is not the primary focus in this scenario.