CompTIA Project+ (PK0-004) — Question 240

A project manager is overseeing a project to analyze large amounts of data to find customer preferences. The large data sets are hosted by an external provider, and the project manager is concerned about losing access to the data.
Which of the following documents is appropriate for use in this situation?

Answer options

Correct answer: B

Explanation

The correct answer is B, the Risk register, as it is specifically used to identify, analyze, and manage risks associated with a project, including concerns about losing data access. The other options do not focus on risk management: A (Project schedule) deals with timelines, C (Action item log) tracks tasks, and D (Issue log) records problems but not potential risks.