CompTIA Project+ (PK0-004) — Question 236

A project manager is overseeing the construction of a new building. There are likely existing underground water, gas, and electrical lines. Which of the following is an example of mitigation?

Answer options

Correct answer: D

Explanation

The correct answer is D because ensuring the contractor has the appropriate utility maps helps prevent damage to existing lines before construction starts. Option A is not a mitigation strategy but rather a reliance on trust, while option B shifts liability rather than preventing issues. Option C addresses damage after it occurs, which is reactive rather than proactive mitigation.