CompTIA Project+ (PK0-004) — Question 214
A testing event was held and deemed unsuccessful. After review, it becomes clear that the two project teams had different expectations of the testing.
Which of the following is needed between the two teams?
Answer options
- A. Communication plan
- B. Project schedule
- C. Status report
- D. Use case
Correct answer: A
Explanation
A communication plan is essential for ensuring that both teams are on the same page regarding expectations and objectives. The project schedule, status report, and use case do not address the fundamental issue of misaligned expectations between the teams.