CompTIA Project+ (PK0-004) — Question 210
A project team member states that the tasks identified in the project schedule for the week greatly exceed the number of available hours for the week. Which of the following activities would have allowed the project manager to identify and correct this issue in advance?
Answer options
- A. Risk identification
- B. Gate review
- C. Resource allocation
- D. Resource leveling
Correct answer: D
Explanation
Resource leveling is the process of resolving resource conflicts by adjusting the project schedule. This would have allowed the project manager to balance the workload against the available hours. The other options, such as risk identification and gate reviews, do not directly address resource scheduling issues.