CompTIA Project+ (PK0-004) — Question 209

After identifying all known tasks, the project manager has started to sequence and set durations.
Which of the following describes how the project manager should BEST determine the initial sequence and durations?

Answer options

Correct answer: A

Explanation

The correct answer is A, as utilizing milestones from the project charter provides clear reference points for sequencing tasks and estimating durations. Options B, C, and D, while potentially useful, do not offer the same level of structured guidance as the milestones in the project charter, which are specifically designed for this purpose.