CompTIA Project+ (PK0-004) — Question 196

Team members in a projectized organization are released at the end of a project and placed on the `bench`. Which of the following should the benched team members do NEXT?

Answer options

Correct answer: B

Explanation

The correct answer is B because checking in with a functional manager is essential for determining the next steps and potential opportunities. The other options are less appropriate as finding a new project or contacting the project manager or sponsor may not be the immediate next step for benched employees.