CompTIA Project+ (PK0-004) — Question 195
Which of the following statements are correct regarding project management? (Choose two.)
Answer options
- A. A project can be part of an organization's program management.
- B. An organization's portfolio will include programs.
- C. A program has a defined start and finish.
- D. An organization's portfolio is a temporary and unique endeavor.
- E. A project portfolio will be managed under program management.
Correct answer: B, C
Explanation
Option B is correct because an organization's portfolio does indeed encompass various programs. Option C is also correct as programs are structured to have specific start and end dates. Options A, D, and E are incorrect because they misrepresent the nature of program management and portfolios in project management.