Which of the following statements are correct regarding project management? (Choose two.)

Answer options

Correct answer: B, C

Explanation

Option B is correct because an organization's portfolio does indeed encompass various programs. Option C is also correct as programs are structured to have specific start and end dates. Options A, D, and E are incorrect because they misrepresent the nature of program management and portfolios in project management.